箱形基础上浮病害整治技术 |
投稿时间:2005-03-26 修订日期:2005-03-26 点此下载全文 |
引用本文:夏彦.箱形基础上浮病害整治技术[J].钻探工程,2005,32(6):1-2.XIA Yan. Treatment for Up Floating Defection Box-foundation[J]. Drilling Engineering, 2005,32(6):1-2. |
摘要点击次数: 912 |
全文下载次数: 476 |
|
|
中文摘要:结合箱形基础不均匀上浮工程病害实例,综合分析了病害原因,提出了应用高压灌浆和抗浮锚杆工艺进行处治的方案。 |
中文关键词:箱形基础上浮 高压灌浆 岩锚 沉降观测 |
|
Treatment for Up Floating Defection Box-foundation |
|
|
Abstract:The causes of engineering defections were analyzed, taking the non-uniform floating in box-foundation. The ways, which are high pressure grouting and anti-lifting anchor piles, to treat the defections were given. |
keywords:box-foundation floating pressure grouting rock anchor subsidence survey |
查看全文 查看/发表评论 下载PDF阅读器 |