地铁竖井开挖设计优化及施工
投稿时间:2005-11-23  修订日期:2005-11-23  点此下载全文
引用本文:黄荣继,祁洪,张宏洲.地铁竖井开挖设计优化及施工[J].钻探工程,2006,33(4):56-58.
HUANG Rong-ji,QI Hong,ZHANG Hong-zhou. Construction and Optimization Design for Subway Shaft Excavation[J]. Drilling Engineering, 2006,33(4):56-58.
摘要点击次数: 1087
全文下载次数: 451
作者单位E-mail
黄荣继 中铁十六局集团北京轨道交通工程建设有限公司 huangrongji_73@yahoo.com.cn 
祁洪 中国地质大学〈北京〉 floodqi@tom.com 
张宏洲 中国地质大学〈北京〉 thirtycat@163.com 
中文摘要:地铁施工中一般采取先竖井继而横通道后开马头门进行正线施工的施工工序。广州轨道交通五号线广州火车站站竖井的开挖方案将原设计优化为在竖井下扩大直接开马头门,在确保结构稳定的同时缩短了工期,减少了二衬背后回填混凝土。
中文关键词:地下铁道  竖井  开挖方案  马头门
 
Construction and Optimization Design for Subway Shaft Excavation
Abstract:The general procedures for constructing subway are as follows: first excavate the shaft, then horizontal pass, finally ingate. The original design for the shaft excavation in Subway Station at Guangzhou Railway Station of Track Traffic Line 5 of Guangzhou was optimized to directly open the ingate by enlarging the lower section of shaft. The time limit for the project was shortened meanwhile the stability of the structure was ensured. The backfill concrete volume after second liner was reduced. That can be used for reference by similar project.
keywords:subway  shaft  excavation alternative  ingate
查看全文  查看/发表评论  下载PDF阅读器