YR-3井井身井管结构设计及固井技术 |
投稿时间:2011-12-15 修订日期:2012-02-03 点此下载全文 |
引用本文:刘文新,张长茂,鲍洪智,等.YR-3井井身井管结构设计及固井技术[J].钻探工程,2012,39(6):35-38.LIU Wen-xin,ZHANG Chang-mao,BAO Hong-zhi,et al. Design of Casing Program for YR-3 Well and the Cementing Technique[J]. Drilling Engineering, 2012,39(6):35-38. |
摘要点击次数: 1171 |
全文下载次数: 817 |
|
|
中文摘要:以YR-3井为例,阐述了牛驮镇地热田从下伏石灰岩-白云岩完整地层钻取地热水时的多级成井结构及固井技术。该技术可有效地克服因地层漏失造成的孔壁坍塌及因设备能力偏小而造成的固井困难。经多眼井施工证明,该方法是牛驮镇地热田及类似地层地热井施工的有效方法。 |
中文关键词:地层漏失 坍塌 多级成井结构 水泥固井 |
|
Design of Casing Program for YR-3 Well and the Cementing Technique |
|
|
Abstract:With the example of YR-3 well, the paper discussed the multilevel well completion structure and cementing technology of drilling for geothermal water in underlying limestone-dolomite complete formation of Niutuozhen geothermal field. With this technology, borehole collapsing caused by circulation loss and cementing difficulties due to low equipment capacity can be effectively solved. Construction of several wells proved that it is a successful and effective method for Niutuozhen geothermal field and the similar ones. |
keywords:circulation loss collapsing multilevel well completion structure slurry cementing |
查看全文 查看/发表评论 下载PDF阅读器 |