大同盆地北部油气预查钻井工程实践
投稿时间:2017-04-12  修订日期:2017-04-12  点此下载全文
引用本文:徐学军.大同盆地北部油气预查钻井工程实践[J].钻探工程,2017,44(6):52-55.
XU Xue-jun. Drilling Engineering Practice of Oil and Gas Pre-exploration in Datong Basin[J]. Drilling Engineering, 2017,44(6):52-55.
摘要点击次数: 968
全文下载次数: 671
作者单位E-mail
徐学军* 山西省地质勘查局二一七地质队 sxdt518@163.com 
中文摘要:大同盆地北部油气预查施工区地层主要为泥岩、砂质泥岩、炭质泥岩和砂砾岩不等厚互层。上部砂砾层胶结松散、破碎,易掉块坍塌;泥岩水敏性强,易分散造浆,护壁困难,钻进中易产生卡钻及粘附卡钻。设计井深一般为1000~3000 m,钻进中合理采用了不同类型、结构的钻头,钻具和取心工具,调整了钻进技术参数,并选用了双聚-成膜无固相钻井液体系及其它相应的工艺技术措施,孔壁稳定,保证了正常施工。其中也顺利完成了侧钻井施工任务,均取得了较好的效果。
中文关键词:油气勘探  取心技术  侧钻井  双聚-成膜无固相钻井液
 
Drilling Engineering Practice of Oil and Gas Pre-exploration in Datong Basin
Abstract:In the oil and gas pre-exploration in northern part of Datong basin, the construction area formation is interbedded mainly with mudstone, sandy mudstone, carbonaceous mudstone and sandy conglomerate, loose cemented gravel in upper part, which are broken with block falling, and mudstone has strong water sensitivity and is easy to disperse and mud making, wall protection is difficult, blocking and sticking occur in drilling process. The designed well depth is generally 1000~3000m, different types and structures of drill bit, tools and coring tool are adopted, drilling parameters are adjusted. Dual polymer filming non-solid drilling fluid system is selected together with corresponding technological process and measures to realize wall stability and the side tracking are successfully completed.
keywords:oil and gas exploration  coring technology  side tracking  dual polymer filming non-solid drilling fluid
查看全文  查看/发表评论  下载PDF阅读器