禹城通裕阳光豪庭基坑工程施工工艺对周边建筑物的影响分析
投稿时间:2018-12-17  修订日期:2019-09-25  点此下载全文
引用本文:毛洁.禹城通裕阳光豪庭基坑工程施工工艺对周边建筑物的影响分析[J].钻探工程,2019,46(10):62-65.
MAO Jie. Influence of the foundation pit construction process in Yucheng on surrounding buildings[J]. Drilling Engineering, 2019,46(10):62-65.
摘要点击次数: 961
全文下载次数: 493
作者单位E-mail
毛洁* 山东省物化探勘查院 903860254@qq.com 
中文摘要:山东禹城通裕阳光豪庭基坑支护工程中因设计及施工工艺对周边建筑物影响较大,针对地层及周边环境对施工工艺及施工顺序进行优化,采用旋喷扩大头锚索,改变支护桩钻进及下笼方法,局部采用SMW工法,施工中加强监测,以上措施确保了工程顺利进行,施工经验可供以后类似工程参考。
中文关键词:基坑支护  桩锚支护  扩大头锚索  水泥土搅拌桩  SMW工法
 
Influence of the foundation pit construction process in Yucheng on surrounding buildings
Abstract:In view of the grave influence on surrounding buildings due to the design and construction process of the Tongyu Yangguang Haoting foundation pit support project, some measures were taken to ensure the smooth progress of the project, such as optimization of the construction process and construction sequence according to the stratum and surrounding environment, adoption of jet grout expanded anchor cables, change of the support pile drilling and rebar cage lowering methods, local adoption of the SMW method, intensification of monitoring during construction. The construction experience can be used as a reference for similar projects in the future.
keywords:foundation pit  pile-anchor support  expanded anchor cable  cement-mixed pile  SMW
查看全文  查看/发表评论  下载PDF阅读器