中文摘要:苏通长江公路大桥主塔基础采用巨型群桩基础,施工前要模拟水上钻孔桩进行钻孔工艺试验,试验钻孔的技术要求高于现行规范要求。介绍了试验钻孔施工技术及取得的成果。
中文关键词:苏通长江公路大桥 主塔基础 钻孔灌注桩 试验钻孔
 
Construction Technology of Testing Borehole in Changjiang Highway Bridge of Suzhou - Nantong
YANG Zong-ren
Abstract:Heavy pile group foundation was taken as the main pylon for Changjiang highway bridge of Suzhou - Nantong, hole boring technique was tested through simulating borehole pile in water before construction by overtopping current specifications. The result of construction technology of testing borehole was introduced in this paper.
keywords:Changjiang highway bridge of Suzhou- Nantong  foundation of main pylon  bored cast-in-place pile  testing borebole