引用本文:林强,郑力会,崔小勃,等.高温高压小井眼尾管固井技术应用[J].钻探工程,2008,35(11):24-26.LIN Qian,ZHENG Li-hui,CUI Xiao-bo,et al. Application of Liner Cementing Technology in HTHP Slim-hole[J]. Drilling Engineering, 2008,35(11):24-26. |
摘要点击次数: 1099 |
全文下载次数: 810 |
|
基金项目:受教育部“长江学者和创新团队发展计划”资助(编号:IRT0411) |
|
中文摘要:高温、高压、深井、小井眼尾管固井是固井技术的一个难点,龙16井在各项配套工程技术措施综合应用的情况下施工成功,为高温、高压、深井固井作业积累了经验。龙16井是川北低平褶皱带九龙山构造上的一口预探井,[JP2]原设计2159 mm井眼钻至下二叠系完钻。由于地质条件复杂,纵向上分布多套产层并具有超高压特点,地层裂缝发育,多次出现涌漏同存复杂情况,被迫提前下入1778 mm套管固井以封隔上部复杂井段。采用1492 mm钻头钻至598800 m完钻并进行了尾管固井作业。固井作业前钻井液密度234 |
中文关键词:深井 高温高压 尾管固井 |
|
Application of Liner Cementing Technology in HTHP Slim-hole |
|
|
Abstract:The liner cementing under high temperature and high pressure in slim-hole is difficult. Well Long-16 is an important preliminary prospecting well in Chuanbei low and flat fold belt of Jiulongshan structure. The original 2159mm hole was designed to complete in Permian, but as well kick and circulation loss happened frequently, 1778mm casing was put down to cement the upper well section ahead of schedule. In this case, 1492mm bit was used to 598800m, and liner cementing was completed. Before cementing, oil gas showed strongly with drilling fluid density of 234g/cm3 and well temperature of 1396℃. |
keywords:deep well HTHP well liner cementing |