梯子崖-富子岭矿区复杂地层钻探技术问题与对策
投稿时间:2016-11-11  修订日期:2017-07-14  点此下载全文
引用本文:祁恩强,朱金军.梯子崖-富子岭矿区复杂地层钻探技术问题与对策[J].钻探工程,2017,44(9):1-6.
QI En-qiang,ZHU Jin-jun. Drilling Technical Problems and Countermeasures in the Complex Formations of Tiziya-Fuziling[J]. Drilling Engineering, 2017,44(9):1-6.
摘要点击次数: 951
全文下载次数: 779
作者单位E-mail
祁恩强* 西北有色地质勘查局七一七总队 gkc717@sina.com 
朱金军 西北有色地质勘查局七一七总队  
中文摘要:陕西省凤县梯子崖-富子岭铅锌多金属矿区,其地层主要为产状较陡的千枚岩,局部含方解石或石英脉,断层破碎带发育,井壁稳定性差,施工中孔斜严重,许多钻孔因孔斜而达不到设计目的,防斜、治斜和泥浆护壁为该矿区施工方面的主要技术难题。文章从孔斜预防、定向造斜、护壁堵漏等方面介绍了所采取的工艺措施和取得的效果。
中文关键词:钻孔偏斜  定向钻进  偏斜器  护壁堵漏  岩心钻探
 
Drilling Technical Problems and Countermeasures in the Complex Formations of Tiziya-Fuziling
Abstract:The formations are mainly of steep occurrence of phyllite in Tiziya-Fuziling lead-zinc polymetallic ore area, locally containing calcite or quartz veins with fault fracture zone development and poor wall stability, the design requirements could not be met because of common severe drilling hole bending. The hole deviation prevention, deviation correction and slurry protection are the major construction technical problems in this mining area. This paper introduces the technical measures taken in hole deviation prevention, directional deflection, wall protection and plugging, as well as the results achieved.
keywords:hole deviation  directional drilling  deflecting wedge  hole wall protection and loss shut-off  core drilling