高位定向钻孔分层布置与瓦斯抽采效果分析
投稿时间:2021-10-18  修订日期:2022-03-17  点此下载全文
引用本文:王永文,姚宁平,王海龙,等.高位定向钻孔分层布置与瓦斯抽采效果分析[J].钻探工程,2022,49(4):117-123.
WANG Yongwen,YAO Ningping,WANG Hailong,et al. Layered layout of high-level directional boreholes and analysis of gas drainage effect[J]. Drilling Engineering, 2022,49(4):117-123.
摘要点击次数: 663
全文下载次数: 818
作者单位E-mail
王永文 山西汾西矿业(集团)有限责任公司山西 介休 032000 hxkwyw@163.com 
姚宁平 中煤科工集团西安研究院有限公司陕西 西安 710077  
王海龙 山西汾西矿业(集团)有限责任公司山西 介休 032000  
张杰* 中煤科工集团西安研究院有限公司陕西 西安 710077 zhangjie@cctegxian.com 
闫志强 山西汾西矿业(集团)有限责任公司山西 介休 032000  
王建强 中煤科工集团西安研究院有限公司陕西 西安 710077 wangjianqiang@cctegxian.com 
贾晓峰 山西汾西矿业(集团)有限责任公司山西 介休 032000  
杜学明 山西汾西矿业(集团)有限责任公司山西 介休 032000  
中文摘要:为了提高顶板高位定向钻孔在采空区及上隅角瓦斯治理的效果,提出了高位定向钻孔分层布孔方案,在曙光煤矿开展现场试验,对不同层位高位定向钻孔瓦斯抽采数据和高位定向钻孔整个瓦斯抽采周期内瓦斯抽采效果分析研究,结果表明高位定向钻孔在整个抽采周期内瓦斯抽采效果总体呈波动状态,中间孔段由于处于顶板裂隙带内,瓦斯抽采效果较稳定,两端孔段由于处于钻孔造斜孔段未进入顶板裂隙带内及受前后钻场钻孔搭接影响,瓦斯抽采效果波动较大。为提高高位定向钻孔瓦斯抽采效果,可采用大角度开孔或大角度螺杆马达造斜以降低造斜孔段长度,并增加相邻两钻场钻孔搭接长度,从而降低两端孔段比例,提高中间孔段比例。
中文关键词:高位定向钻孔  采空区  瓦斯抽采  分层布置  抽采周期
 
Layered layout of high-level directional boreholes and analysis of gas drainage effect
Abstract:In order to improve the effect of high-level directional drilling in the roof on the goaf and upper corner gas control, a layered arrangement of high-level directional boreholes was proposed, and field tests were carried out in Shuguang Coal Mine. Analysis of gas drainage data of high-level directional boreholes at different depth, and gas drainage effect of high-position directional boreholes in the entire gas drainage cycle showed that gas drainage effect of high-position directional boreholes fluctuated throughout the entire drainage cycle in general. Drainage effect was relatively stable over the middle hole section since it was located in the roof crack zone; while gas drainage effect fluctuated greatly over both top and bottom hole sections since they were located in the build-up sections of the drill holes and did not enter the roof fissure zone, and were affected by the overlap of the drainage holes from the front and rear drill sites. In order to improve gas drainage effect of high-position directional drilling, a large entry angle or a high-bent mud motor can be used to reduce the length of the build-up hole section and increase the overlap length of the drainage holes from the two adjacent drilling sites so as to reduce the proportion of both top and bottom hole sections, and increase that of the middle hole section.
keywords:high-level directional drilling  mined-out area  gas drainage  layered layout  drainage cycle
查看全文  查看/发表评论  下载PDF阅读器