Treatment Technology for Drilling Pipe Sticking Accident in Directional Well
DOI:
CSTR:
Author:
Affiliation:

Clc Number:

TE249

Fund Project:

  • Article
  • |
  • Figures
  • |
  • Metrics
  • |
  • Reference
  • |
  • Related
  • |
  • Cited by
  • |
  • Materials
  • |
  • Comments
    Abstract:

    Drilling pipe sticking accident occurred in HDR29D geothermal well, which was overcome by the accident cause analysis, stuck-releasing scheme study and stuck-pipe freeing agent compounding. The paper summed up the causes of drilling pipe sticking in directional well and the treatment method.