    Abstract:

    Kazan Trona Mine in Turky is characterized by complicated geological settings, high content of insolubles in the primary mining layer and high dip angles of ore beds, which leads to frequently blockage problems during commercial solution mining. This paper takes Unit P078 horizontal intersected well as an example to describe the drilling techniques and leaching history, and analyze the causes of blockage. By following the principle of “from easy to difficult, minimizing risks and controlling the cost”, various attempts were taken to deal with the problem, such as single well circulation, pressurizing the channel by cementation truck, and circulating drilling mud to clean the borehole, and finally, it was decided that sidetracking was applied to drill a lateral to connect both targets, and it was proved to be successful with minimum costs and low risks. Some suggestions related to construction, design, repair and solution mining operations were put forward. The experience can provide some guidance and reference for solving blockage problems in the similar scenario.

    Reference
    [1] 胡汉月, 向军文, 刘海翔等. SmartMag定向中靶系统工业试验研究[J]. 探矿工程(岩土钻掘工程). 2010, 37(4):6-10.HU Hanyue, XIANG Junwen, LIU Haixiang, etc. Industrial Test Research on SmartMag Target-hitting Guidance System[J]. Exploration Engineering (Rock Soil Drilling and Tunneling), 2010, 37(4):6-10.
    [2] 向军文, 胡汉月. 国产定向对接井精确中靶技术在盐矿中的应用[J]. 中国井矿盐. 2010, 41(5):16-18.XIANG Junwen, HU Hanyue. The Application of Accurate Target Technology of Domestic Directional Butted-Wells in Salt Mine[J]. China Well and Rock Salt. 2010, 41(5):16-18.
    [3] 陈剑垚,胡汉月.SmartMag定向钻进高精度中靶系统及其应用[J].探矿工程(岩土钻掘工程),2011,38(4):10-12.CHEN Jianyao, HU Hanyue. Experience on application of SmartMag high precision drilling guidance system[J]. Exploration Engineering (Rock Soil Drilling and Tunneling), 2011,38(4):10-12.
    [4] 向军文, 胡汉月, 刘志强. 土耳其天然碱矿30对对接井钻井工程[J]. 中国井矿盐. 2007, 38(5):25-28.XIANG Junwen, HU Hanyue, Liu Zhiqiang. Well Drilling in 30 Pairs of Butted Wells in a Trona Mine in Turkey[J]. China Well and Rock Salt.2007,38(5):25-28.
    [5] 隆东, 张新刚, 岳刚等. H024井施工工艺及精确中靶技术措施[J]. 探矿工程(岩土钻掘工程). 2011, 38(3):5-8, 12.LONG Dong, ZHANG Xingang, Yue Gang, etc. Construction Technology of Well H024U and the Technical Measures of Accurate Target Hitting[J]. Exploration Engineering (Rock Soil Drilling and Tunneling), 2011, 38(3):5-8, 12.
    [6] 李鑫淼, 张永勤, 尹浩等. 水平对接井钻井技术在天然气水合物试采中的应用[J]. 探矿工程(岩土钻掘工程), 2017,44(8):13-17.LI Xinmiao, ZHANG Yongqin, Yin Hao, etc. the Application of Horizontal Butted Well Drilling Technology in the Test Mining of Natural Gas Hydrate[J]. Exploration Engineering (Rock Soil Drilling Tunneling), 2017, 44(8):13-17.
    [7] 商敬秋, 武程亮,刘汪威等. 无建槽直井的定向中靶作业[J]. 探矿工程(岩土钻掘工程). 2014, 41(1):13-16.SHANG Jingqiu, WU Chengliang, Liu Wangwei, etc. Oriented Target-hitting Operations for Vertical Well without Cavity Building[J]. Exploration Engineering (Rock Soil Drilling and Tunneling),2014, 41(1):13-16.
    [8] 胡汉月. 对接中靶区建槽若干问题探讨[J]. 探矿工程(岩土钻掘工程). 2014, 41(7):20-23.HU Hanyue. Discussion of Cavity Development in the Target Area of Intersection Well Pair[J]. Exploration Engineering (Rock Soil Drilling and Tunneling),2014, 41(7):20-23.
    [9] 樊传忠. 盐矿水平对接井开采的几个关键问题[J]. 中国井矿盐. 2015,45(5):13-16, 46.FAN Chuanzhong. Essential Issues of Horizontal Butted Well Mining[J]. China Well and Rock Slat. 2015, 45(5):13-16,46.
    [10] 那云宏, 苏祖军, 胡炜. 乔后盐矿斜井溶腔形状初探[J]. 中国井矿盐. 2014, 45(6):19-20.NA Yunhong, SU Zujun, HU Wei. Preliminary Study on Salt Mine Inclined Shaft Cavity Shape of Qiaohou[J]. China Well and Rock Slat. 2014, 45(6):19-20.
    [11] 刘联群, 米丰忠, 崔秀忠. 水平对接盐井溶腔形状探讨[J]. 中国井矿盐. 2014, 45(4):23-25.LIU Lianqun, MI Fengzhong, CUI Xiuzhong. Discussion of Shapes of Dissolved Chamber of Horizontal Docking Salt Well Cavities. China Well and Rock Salt.2014,45(4):23-25.
    [12] 陈必权. 浅谈水平连通卤井堵塞的原因与处理[J]. 中国井矿盐. 2014, 45(1):18-20.CHEN Biquan. Brief Introduction on the Causes of Block of Horizontal Docking Wells and the Treatment. China Well and Rock Salt.2014,45(1):18-20.
    [13] 任松, 唐康, 易亮等. 小间距双井水溶造腔腔体扩展特性[J]. 东北大学学报(自然科学版), 2017, 38(11):1654-1658.REN Song, TANG Kang, YI Liang, etc. Properties of Two-Well Dissolution Cavity-Building Expansion with Small Well Space[J]. Journal of Northeastern University (Natural Science). 2017, 38(11):1654-1658.
    [14] 高丽, 苏如海, 戴鑫等. 盐井水溶开采上溶速度影响因素研究[J].中国井矿盐. 2017, 48(6):11-13.GAO Li, SU Ruhai, DAI Xin, etc. The Study of Main Fluential Elements for the Up-dissolved Rate of Production of the Salt Well[J]. China Well and Rock Salt. 2017, 48(6):11-13.
    Cited by
Get Citation
Share
Article Metrics
  • Abstract:1195
  • PDF: 1096
  • HTML: 254
  • Cited by: 0
History
  • Received:March 31,2020
  • Revised:July 09,2020
  • Adopted:July 15,2020
  • Online: August 19,2020
Article QR Code